Venue |
Project/Procurement Description |
Responsible Party |
Actual/Target Issue Date |
Actual/Target Due Date |
Actual/Target Selection/
Authorization |
Notes/Selection |
|
|
|
|
|
|
|
|
|
Dr. Phillips Center |
South Street Realignment (Rosalind
to Orange Ave) - Construction Procurement |
City |
4/20/2011* |
5/23/2011* |
9/2011 |
Bids received are under review.
|
|
Dr. Phillips Center |
Developer’s Representative Services Request for Qualifications |
Orlando Community Construction
Corporation (OCCC) |
3/11/2011* |
3/31/2011* |
4/11/2011* |
PCL Construction Services selected; Visit:
http://www.drphillipscenter.org/progress/
design/requests_for_proposals/archives for detailed information. |
|
Dr. Phillips Center |
Construction Material Testing RFQ |
Dr. Phillips Center |
10/15/2010* |
11/5/2010* |
2/8/2011* |
Nodarse and Associates selected; Visit
http://www.drphillipscenter.org/progress/
design/requests_for_proposals/archives
for detailed information. |
|
Dr. Phillips Center |
Threshold Inspection RFQ |
Dr. Phillips Center |
10/15/2010* |
11/5/2010* |
1/12/2011* |
Universal Engineering Sciences, Inc. selected; Visit
http://www.drphillipscenter.org/progress/
design/requests_for_proposals/archives
for detailed information. |
|
Dr. Phillips Center |
Invitation to Bid on Stage One |
Balfour Beatty Construction |
9/20/2010* |
11/4/2010*; 11/11/2010* |
11/2010 |
Stage 1 of this project has been bid. Contact Bob Jankovich at
Balfour Beatty Construction (407-226-9819) with any questions.
Visit
http://www.drphillipscenter.org/progress/
construction
for more information. |
|
Dr. Phillips Center |
Systems Integrator Services Request for Proposals |
Dr. Phillips Center |
2/24/2010* |
3/25/2010* |
8/6/2010* |
Harris IT Services Corporation selected |
|
Dr. Phillips Center |
Developer Controlled Insurance Program (DCIP) Request for
Proposal |
Dr. Phillips Center |
3/2/2010* |
4/15/2010* |
5/2010 |
The Dr. Phillips Center for the Performing Arts opted for a
Contractor Controlled Insurance Program (CCIP). |
|
Dr. Phillips Center |
Demolition of Orlando Fire Station 1 at 439 S. Magnolia Ave.
Invitation to Bid |
City |
2/4/2010* |
3/4/2010* |
3/15/2010* |
Maximus Demolition, LLC awarded |
|
Dr. Phillips Center |
Architectural Model Making Services Request for Proposals |
Dr. Phillips Center |
9/1/2009* |
9/18/2009* |
12/2/2009* |
Presentation Studios International, LLC selected |
|
Dr. Phillips Center |
Sold CRA Bonds |
City |
|
|
9/3/2009* |
|
|
Dr. Phillips Center |
Art Consultant Request for Proposals |
Dr. Phillips Center |
7/17/2009* |
8/3/2009* |
8/19/2009* |
Bobosart selected |
|
Dr. Phillips Center |
Construction Manager at Risk Request for Proposals, Part 1 & 2 |
Dr. Phillips Center |
9/29/2008*; 6/18/2008* |
10/30/2008*; 8/14/2008* |
7/13/2009*; 12/8/2008*; 11/19/2008*; 9/2/2008* |
Balfour Beatty Construction |
|
Dr. Phillips Center |
South Street Realignment (Rosalind to Orange Ave) – Design
Services Request for Qualification Statements |
City |
6/16/2008* |
7/2/2008* |
12/15/2008*; 9/8/2008*; 7/29/2008* |
Lochrane Consulting Engineers and Surveyors
|
|
Dr. Phillips Center |
Building Management and Control Systems Request for Proposal |
Dr. Phillips Center |
8/20/2008* |
9/5/2008* |
11/26/2008* |
HMA selected |
|
Dr. Phillips Center |
Food Service Design Consultant Request for Proposal |
Dr. Phillips Center |
9/4/2008* |
9/24/2008* |
11/26/2008* |
Systems Design International (SDI) selected
|
|
Dr. Phillips Center |
Commissioning Consultant Request for Proposal |
Dr. Phillips Center |
8/20/2008* |
9/12/2008* |
11/26/2008* |
Green Building Services with Chinook Systems, Inc. selected
|
|
Dr. Phillips Center |
Wayfinding Graphics Consultant Request for Proposals |
Dr. Phillips Center |
5/13/2008* |
6/5/2008* |
7/28/2008* |
Sussman/Prejza & Co., Inc. selected |
|
Dr. Phillips Center |
Audio/Video Consultant Request for Proposals |
Dr. Phillips Center |
5/13/2008* |
6/5/2008* |
6/30/2008*
|
Artec Consultants, Inc. w/ Quietly Making Noise, LLC. selected
|
|
Dr. Phillips Center |
ADA/Accessibility Consultant Request for Qualifications |
Dr. Phillips Center |
2/12/2008* |
2/29/2008* |
6/3/2008* |
Accessology selected |
|
Dr. Phillips Center |
Reprographics and Document Management Request for Proposals |
Dr. Phillips Center |
2/13/2008* |
2/29/2008* |
5/13/2008* |
Winter Park Blue with LDI Reproprinting Centers selected |
|
Dr. Phillips Center |
Architectural Lighting Consultant Request for Proposals |
Dr. Phillips Center |
2/11/2008* |
2/29/2008* |
3/11/2008* |
Horton Lees Brogden Lighting Design selected |
|
Dr. Phillips Center |
Sustainability Consultant Request for Proposals |
Dr. Phillips Center |
2/11/2008* |
2/29/2008* |
3/11/2008* |
Green Building Services
selected |
|
Dr. Phillips Center |
Food Service Programming Consultant Request for Proposals |
Dr. Phillips Center |
12/21/2007* |
1/18/2008* |
3/11/2008* |
JGL Management Services Co. selected |
|
Dr. Phillips Center |
Building Envelope Consultant (waterproofing, roofing, curtain
wall, and window wall consultant) Request for Qualifications |
Dr. Phillips Center |
2/11/2008* |
2/29/2008* |
3/5/2008* |
Curtainwall Design Consultants selected |
|
Dr. Phillips Center |
Elevator Consultant Request for Qualifications |
Dr. Phillips Center |
2/11/2008* |
2/29/2008* |
3/5/2008* |
Persohn Hahn Associates, Inc. selected |
|
Dr. Phillips Center |
Public Relations Consultant |
Dr. Phillips Center |
12/18/2007* |
1/18/2008* |
3/4/2008* |
Edelman Inc. w/TJM Consultants, Inc. selected |
|
Dr. Phillips Center |
Landscape Architects Consultant Request for Proposals |
Dr. Phillips Center |
12/21/2007* |
1/18/2008* |
2/5/2008* |
Murase Associates w/JCR Consulting selected |
|
Dr. Phillips Center |
Mechanical/Electrical/Plumbing Engineering Consultant Request
for Proposals |
Dr. Phillips Center |
12/21/2007* |
1/18/2008 |
2/7/2008* |
TLC w/ARUP & SGM selected |
|
Dr. Phillips Center |
Structural Engineering Consultant Request for Proposals |
Dr. Phillips Center |
12/21/2007* |
1/18/2008* |
1/31/2008* |
TLC w/ARUP, Brindley Pieters & Base selected |
|
Dr. Phillips Center |
Code/Fire Protection Consultant Request for Proposals |
Dr. Phillips Center |
12/21/2007* |
1/18/2008* |
1/31/2008* |
Hughes Associates selected |
|
Dr. Phillips Center |
Civil Engineering Consultant Request for Proposals |
Dr. Phillips Center |
12/21/2007* |
1/18/2008* |
1/29/2008* |
WBQ w/ Lochrane/HDR Engineering selected |
|
Dr. Phillips Center |
Geotechnical Engineering Consultant Request for Proposals |
Dr. Phillips Center |
12/21/2007* |
1/18/2008* |
1/29/2008* |
Universal Engineering w/Law Associates selected |
|
Dr. Phillips Center |
City ROW Survey Services, Continuing Services Agreement,
Services Authorization |
City |
|
11/28/2007* |
1/22/2008* |
PEC Engineering |
|
Dr. Phillips Center |
Production Architect Request for Proposals |
Dr. Phillips Center |
8/27/2007* |
9/14/2007* |
10/15/2007* |
HKS/Baker Barrios selected |
|
Dr. Phillips Center |
M/WBE Consultant Request for Proposals |
Dr. Phillips Center |
8/27/2007* |
9/14/2007* |
10/15/2007* |
Anderson & Assoc. selected |
|
Dr. Phillips Center |
Banking Partner Request for Proposal |
Dr. Phillips Center |
8/7/2007* |
8/24/2007* |
10/11/2007* |
Bank of America |
|
Dr. Phillips Center |
Theater Construction Cost Management Consultant Request for
Proposals |
Dr. Phillips Center |
8/15/2007* |
8/30/2007* |
9/24/2007* |
Donnell Consultants, Inc. selected |
|
Dr. Phillips Center |
Theater Planning Consultant Request for Proposals |
Dr. Phillips Center |
8/27/2007* |
9/14/2007* |
9/24/2007* |
Theatre Project Consultants selected |
|
Dr. Phillips Center |
Acoustical Design Consultant Request for Proposals |
Dr. Phillips Center |
8/27/2007* |
9/14/2007* |
9/24/2007* |
ARTEC selected |
|
Dr. Phillips Center |
Community Inclusion Forum/Design Consultants Pre-proposal
Conference |
Dr. Phillips Center |
8/22/2007* |
N/A |
N/A |
|
|
Dr. Phillips Center |
Design Architect and Master Plan Architect Selection |
Dr. Phillips Center |
|
|
1/2006* |
Barton Myers Associates and EE&K |
|
|
|
|
|
|
|
|
|
Amway Center |
Peer Group Security Services for
Orlando Venues Request for Proposals |
City |
5/7/2010* |
6/9/2010* |
7/30/2010* |
Andy Frain Services, Inc. |
|
Amway Center |
Janitorial Services for Orlando
Venues Request for Proposals |
City |
5/4/2010* |
6/2/2010* |
7/30/2010* |
Owens, Renz & Lee Co., Inc. |
|
Amway Center |
Distributed Antenna System Request
for Proposals |
City |
3/30/2010* |
5/5/2010* |
5/24/2010* |
Crown Castle Solutions Corp. |
|
Amway Center |
Point of Sale System Request for
Proposals |
Magic |
4/19/2019* |
5/4/2010* |
5/17/2010* |
Micros Systems, Inc. |
|
Amway Center |
Ticketing Management & Distribution
System Request for Proposals |
Magic |
2/15/2010* |
3/31/2010* |
4/23/2010* |
Ticket Master Ranked #1 in Primary &
Secondary Markets |
|
Amway Center |
Artwork Consultation Services
Request for Proposals |
Magic |
1/25/2010* |
2/16/2010* |
3/24/2010* |
Sports and Arts selected
|
|
Amway Center |
Arbitration/Mediation Services
Request for Letters of Interest and Qualifications |
Magic |
1/20/2010*
|
2/3/2010* |
TBD |
|
|
Amway Center |
Food Service Management at the Amway
Center, Bob Carr Performing Arts Centre and Florida Citrus Bowl
Request for Proposals |
City |
11/17/2009* |
1/7/2010* |
2/22/2010* |
Orlando Foodservice Partners
|
|
Amway Center |
Closed on Covenant Bonds for the
Parking Garage |
City
|
|
|
9/16/2009* |
|
|
Amway Center |
Scoreboard & Display Systems Request
for Proposals |
Magic |
5/29/2009* |
7/2/2009* |
9/25/2009* |
Daktronics, Inc.
|
|
Amway Center |
Site Utility Relocation Design
Services – Continuing Services Agreement, Services Authorization
–Retention Pond P6 Modifications |
City |
|
|
8/10/2009*; 8/4/2008*; 3/3/2008* |
PEC Engineering |
|
Amway Center |
Parking Garage Threshold Inspection
Services RFQ |
City |
5/17/2009* |
6/1/2009* |
7/13/2009*; 6/22/2009* |
Universal Engineering Sciences, Inc. |
|
Amway Center |
Parking Garage Materials Testing
Services RFQ |
City |
5/17/2009* |
6/1/2009* |
7/13/2009*; 6/22/2009* |
Ardaman & Associates, Inc. |
|
Amway Center |
Furniture, Fixtures, and Equipment
(FF&E) Contractor Request for Proposals |
Magic |
4/14/2009* |
5/7/2009* |
5/20/2009* |
TeKONTROL, Inc. and Facility
Management Services Group (FMSG), as a joint venture selected |
|
Amway Center |
Stormwater Pond P6 Modifications
Construction Invitation to Bid |
City |
3/2/2009* |
3/31/2009* |
4/13/2009* |
Emerald Utilities and Site
Development, Inc. selected |
|
Amway Center |
Roadway, Streetscape, & Utility
Improvements Design/Build Services Request for Proposals |
City |
5/18/2008* |
6/9/2008* |
2/2/2009*; 10/6/2008*; 8/4/2008*;
7/9/2008* |
Gomez Construction Co. |
|
Amway Center |
Streetscape – Professional Landscape
Architecture Design Services Request for Qualification
Statements |
City |
1/28/2008* |
2/15/2008* |
9/8/2008*; 3/17/2008* |
Glatting Jackson Kercher Anglin,
Inc. |
|
Amway Center |
Site Utility Relocation Design
Services – Continuing Services Agreement, Services Authorization
–Various Utilities and Communication Duct Bank |
City |
|
|
6/23/2008*; 6/2/2008*; 4/21/2008*;
2/11/2008*; 9/10/2007*; 8/20/2007* |
Carter-Burgess |
|
Amway Center |
Parking Garage Design-Build Services
Request for Proposals |
City
|
11/25/2007* |
12/26/2007* |
6/2/2008*; 2/11/2008* |
PCL Construction Services, Inc. |
|
Amway Center |
Professional Service Firms
(Threshold Inspection & Materials Testing) Request for
Qualifications |
Magic |
3/10/2008* |
3/27/2008* |
6/2/2008*; 4/14/2008* |
Universal Engineering Sciences, Inc.
for Threshold Inspection. Nodarse and Associates, Inc. for Construction Materials Testing & Inspection. |
|
Amway Center |
Site Utility Relocation Construction
Procurement –Church/Hughey Sanitary – Rapid Response Contractors |
City |
5/1/2008* |
5/22/2008* |
5/28/2008* |
A & M SI Construction Co., Inc. |
|
Amway Center |
Issuance of Tourist Development Tax
Revenue Bonds, Series 2008 A, B & C |
City
|
|
|
3/13/2008* |
A & B: Citigroup Capital Markets and
Goldman Sachs & Co.; C: Goldman Sachs & Co. |
|
Amway Center |
Issuance of State Sales Tax Payments
Revenue Bonds, Series 2007 |
City |
2007 |
2/26/2008* |
3/6/2008* |
Regions Bank listed as Registrar and
Paying Agent. Jackson Securities LLC listed as Underwriter. |
|
Amway Center |
M/WBE Coordinator Request For
Proposals |
Magic |
9/17/2007* |
10/3/2007* |
3/4/2008* |
Selected B&L Management Consulting Group, Inc. |
|
Amway Center |
Site Demolition Services –
Continuing Services Agreements, Services Authorization |
City |
|
|
10/2007 – 1/2008* |
HB Walker, Global |
|
Amway Center |
Site Utility Relocation Construction
Procurement – Division/Church Sanitary & Stormwater – Rapid
Response Contractors |
City |
11/2007* |
12/21/2007* |
1/2008* |
CE James |
|
Amway Center |
Insurance Brokerage Services Request
For Proposals |
Magic |
11/5/2007* |
12/4/2007* |
12/14/2007* |
Marsh USA, Inc selected |
|
Amway Center |
Traffic Analysis—Continuing Services
Agreement, Services Authorization |
City
|
|
|
11/12/2007* |
GMB |
|
Amway Center |
Construction Manager at Risk “Most
Qualified” Request for Proposals |
Magic |
9/24/2007* |
10/12/2007* |
10/23/2007* |
Selected Hunt Construction Group with Rey Group, R.L. Burns
Inc., HZ Construction and Albu & Associates Inc, as
in-association CM partners |
|
Amway Center |
Environmental Remediation Request
for Proposals |
City
|
8/30/2007* |
9/26/2007* |
10/15/2007* |
Geo-Cleanse |
|
Amway Center |
Green Champion Request For Proposals |
Magic |
9/17/2007* |
10/3/2007* |
10/5/2007* |
TLC selected |
|
Amway Center |
Design Consultants Request for
Qualifications |
Magic |
8/13/2007* |
8/24/2007* |
9/27/2007* |
Link to selection announcement |
|
Amway Center |
Geotechnical Engineer Request for
Qualifications |
Magic |
8/13/2007* |
8/24/2007* |
9/27/2007* |
Nodarse selected |
|
Amway Center |
Construction Manager at Risk Request
for Qualifications |
Magic |
8/27/2007* |
9/13/2007* |
9/18/2007* |
“Most Qualified” Firms:
Hunt Construction; PCL Construction, Barton Malow, and JCB
Construction joint venture; Skanska USA and JCB Construction
joint venture; and Austin Commercial and Hardin Construction
joint venture |
|
Amway Center |
Design Professional Request for
Proposals |
Magic |
5/30/2007* |
6/21/2007* |
8/3/2007* |
HOK Sport, Walter P. Moore, Smith
Seckman Reid selected |
|
Amway Center |
Surveying Services—Continuing
Services Agreement, Services Authorization |
City
|
|
|
2006-2007* |
ConsulTech |
|
|
|
|
|
|
|
|
|
Florida Citrus Bowl |
Construction Manager at Risk
Services for FCB Renovations Phase 1 Request for Proposals |
City
|
2/1/2010* |
3/3/2010* |
5/10/2010*; 4/12/2010* |
Turner Construction Co. |
|
Florida Citrus Bowl |
Architectural/Engineering Services
Related to the Renovation of the Florida Citrus Bowl Request for
Qualifications |
City
|
10/22/2007* |
11/19/2007* |
5/10/2010*; 10/6/2008*; 1/14/2008* |
HNTB Architecture Inc. |
|
Florida Citrus Bowl |
Design Criteria
Professional—Continuing Professional Consulting Agreement
Services Authorization. |
City
|
|
|
7/9/2007* |
GAI Consultants |
|
|
|
|
|
|
|
|
|
ALL |
Fabrication & Installation of the
Downtown Orlando Wayfinding Sign System Request for Proposals |
City |
12/4/2009* |
1/6/2010* |
2/1/2010* |
City Council approved selection of
two (2) top ranked firms, pending negotiations: 1. The Baron
Group, dba Baron Sign Manufacturing; 2. Design Communications
LTD |
|
ALL |
Financial Advisor Request for
Proposals |
City |
2010 |
2010 |
TBD |
|
|
ALL |
Bond Counsel Request for Proposals |
City |
2010 |
2011 |
TBD |
|
|
ALL |
Community Venues Design and
Construction Owner’s Representative Services Request for
Qualifications |
City
|
8/20/2007* |
9/13/2007* |
11/17/2008*; 10/15/2007* |
URS
selected |
|
ALL |
Blueprint Workforce Initiative
Grant, Initial Proof of Concept Phase |
City |
2/25/2008* |
3/21/2008* |
5/5/2008* |
Four short-listed firms approved for
grant period funding: Nehemiah Educational and Economic
Development, Inc. (N.E.E.D.S.); Community Service Center of
Central Florida, Inc.; Center for Change, Inc. (Resource
Solutions); and Community and Church Assistance Program |
|
ALL |
Select Bond Trustee RFP Process |
City |
10/2007* various |
2007* |
2007* |
Wells Fargo was chosen as Trustee
for the TDT Bonds |
|
ALL |
Select Structured Product
Investments for Construction Proceeds |
City |
10/2007* various |
N/A |
N/A |
will be chosen at each bond deal
|
|
ALL |
Investment Banking Team RFP Process |
City |
8/2/2007* |
8/22/2007* |
9/10/2007* |
|