The Orlando House, Florida's Future

 

 

Throughout the construction process, a photo archive was kept to track the progress of the Orlando House. 

                    

 

       Lot at acquisition - 2001
         Lot Cleared - January 3, 2002
         Footers and Stem wall - January 22, 2002
         Slab poured - February 15, 2002
         Steel Framing - February  19 - 21, 2002
         Sheathing installation - March 21, 2002
         The 2nd Floor, Porch and Garage - April 15, 2002
         Steel Roof Trusses Installed - April 29, 2002
         Tyvek and Fire Sprinklers Installed - June 5, 2002
         Icynene Insulation Completed - June 11, 2002
         HardiPlank Smooth Lap Siding Installed - July 12, 2002

         Metal Roofing Completed - August 22, 2002
         All rough-ins completed - September 5, 2002

         Drywall installation completed - October 10, 2002

         Kitchen Cabinets - October 22, 2002
         Staircase is assembled and painted - October 28, 2002

         Stucco - November 1, 2002

         Landscaping - December 14, 2002

         Driveway Pavers - November 22, 2002    

 