Throughout the construction process, a photo archive was kept to track the progress of the Orlando House.
Lot at acquisition - 2001 Lot Cleared - January 3, 2002 Footers and Stem wall - January 22, 2002 Slab poured - February 15, 2002 Steel Framing - February 19 - 21, 2002 Sheathing installation - March 21, 2002 The 2nd Floor, Porch and Garage - April 15, 2002 Steel Roof Trusses Installed - April 29, 2002 Tyvek and Fire Sprinklers Installed - June 5, 2002 Icynene Insulation Completed - June 11, 2002 HardiPlank Smooth Lap Siding Installed - July 12, 2002
Metal Roofing Completed - August 22, 2002 All rough-ins completed - September 5, 2002
Drywall installation completed - October 10, 2002
Kitchen Cabinets - October 22, 2002 Staircase is assembled and painted - October 28, 2002
Stucco - November 1, 2002
Landscaping - December 14, 2002
Driveway Pavers - November 22, 2002